Temporary Bracing
- No one should be allowed on the Open Joist™ system until all hangers, blocking, rim board, and temporary bracing are completely installed.
- Open Joist must be held straight and plumb at their design
spacing while all blocking, rim board and bracing are installed.
- Temporary bracing is required at all supports and at the interval shown in the drawing until permanent bracing elements and sheathing are installed.
- Cantilevers require lateral bracing at ends.
- Lateral Bridging and Bracing
- Installation of permanent strongback bracing for the purpose of load sharing is recommended.
- Permanent bracing to transmit lateral forces or to provide stability in some applications may be required and should be specified by the building designer.